Gateway Facility Construction Photos


West end of Bldg. - Steel Erection. (March 2, 2005)

West end of Bldg. - Steel Erection. (March 2, 2005)

West end of Bldg. - Steel Erection. (March 2, 2005)

East end of Bldg. Site - Blankets covering remaining North; slab planned to be poured on Friday 3/4/05. (March 2, 2005)

Looking north, open trench (with snow) for relocation of communications duct bank.

Looking north, open trench (with snow) for relocation of communications duct bank.

Existing communications tie-in manhole on north side of Eniwetok (Thermally hot to touch, being impacted by leak from adjacent steam line)

Steam outlet grate is north of hot communications manhole.

Open trench for relocation of 13.2 KV line looking south towards Sigma Building security fence.

End of open trench for 13.2 KV line with Sigma Building security fence and tie-in manhole just beyond fence.

Concrete Placement at Column Line 10. This column line is the Eastern most end of the building. (January 10, 2005)

West end of site - Entry and Elevator Pit. (January 7, 2005)

East end of building - Men placing reinforcing steel in Spot Footing F13. Backhoe and Lift just west of Spot Footing F13. (January 7, 2005)

East end of site concrete placement. Sanitary sewer for construction trailers (white/blue crane/yellow transportainer). Bottom left quadrant of photo shows spot footing F13. Left center of photo indicated column line 10 footing concrete placement. (January 7, 2005)

View of approx. 60% of the building site from the MST OB roof. This photo with IMG_0292R.jpg covers approx. 90% of the building footprint. (January 7, 2005)

NW End of Site from roof of MST OB - Top left quadrant of photo included building entry and elevator pit. Building entry is Column Line 1 and the Western most end of the buiding. (January 7, 2005)

Beginning placement of Spot Footing F11. (January 7, 2005)

West portion of building. (January 19, 2005)

East portion of building from MST OB roof. (January 19, 2005)

View of most of Gateway site from MST OB roof. (January 19, 2005)

West portion of Site from MST OB roof. (January 19, 2005)

East portion of Site from MST OB roof. (January 19, 2005)

Future Gateway Site looking South - main entry at bottom right. (January 19, 2005)

Entry and North Wall looking East. (January 19, 2005)

NE Corner of Bldg. looking NW. (January 19, 2005)

Temp. Power Looking West. (February 1, 2005)

Temp. Power Looking SW. (February 1, 2005)

Temp. Power Looking NW. (February 1, 2005)

Stem/Ret. Wall SW Corner. (February 1, 2005)

South end of Bldg. (February 1, 2005)

East end of Site - Snow being taken off-site. (February 1, 2005)

East portion of Site. (February 1, 2005)

West end of Site. (February 1, 2005)

West end of Site. (February 17, 2005)

Center of Site looking North. (February 17, 2005)

East end of Site. (February 17, 2005)

NW Corner of Site. (February 17, 2005)

Pouring gas cyl. storage - south end of bldg. (February 23, 2005)

Crane looking NW. (February 23, 2005)

West end of Site. (February 23, 2005)

Central portion of Site looking North. (February 23, 2005)

East end of Bldg. (February 23, 2005)

East end of constr. area looking NE - Constr. trlrs. behind large pine tree. (February 23, 2005)

Plumbing/Electr. @ 4,6 & B,C - Slab for gas cyl. (February 23, 2005)

Crane & Steel Columns. (February 23, 2005)

Crane from MST OB Roof. (February 23, 2005)

Pouring North 8: thk. slab - excav. for electr. work - underslab plumbing. (February 28, 2005)

West end of site - pouring 8" thk. slab/excav. for electr. (February 28, 2005)

Center of site looking North. (February 28, 2005)

East end of Site - Concrete pumping 8" thk. North slab. (February 28, 2005)

Pouring North 8"thk. slab. (February 28, 2005)

Pouring North 9" thk. slab . (February 28, 2005)

Closeup - Pouring North 8: thk. slab. (February 28, 2005)

Setting in/bolting steel columns. (February 28, 2005)

Setting steel columns in place. (February 28, 2005)

Steel delivery for placement. (February 28, 2005)

Completing pour of approx. 60% of North 8: thk. slab & other work looking NNE. (February 28, 2005)

Pouring 8" thk. concrete slab @ West end. (March 9, 2005)

8" thk. slab at West end. (March 9, 2005)

Concrete pumping to South 8" thk. slab looking WSW. (March 9, 2005)

Looking straight north across the structure. (March 21, 2005)

View to north from south side of site. (March 21, 2005)

North but showing the first floor area. (March 21, 2005)

Northeast view. (March 21, 2005)

Bar joists to be used for the ceiling. (March 21, 2005)

The west of the site but looking east. (March 21, 2005)

View to southeast from Eniwetok Dr. (March 21, 2005)

View to the southwest from Eniwetok Dr. (March 21, 2005)

View to west from east side of site. (March 21, 2005)

View to NW from SE corner of site. (March 21, 2005)

A view looking northeast from the 2nd floor of the MSTOB. (March 24, 2005)

A view looking northwest from the southeast corner of the site. (March 24, 2005)

A plan view drawing of the first floor. The white area represents the area to be poured tomorrow. We expect it to be in yellow next week. (March 24, 2005)

The view looking north from the same location. Photo #5 shows a magnified view with the welders visible and working on the bar joists. (March 24, 2005)

The big crane is slated for the move to the east side of the site next Wednesday night/Thursday morning. Following that HP will begin to set the structural steel from columns 6 - 10.

Pouring SOG, Grid Lines 5 to 7 & B to D. (March 18, 2005)

West end of bldg., steel, & second flr. decking. (March 18, 2005)

West end of bldg. (March 18, 2005)

Pouring slab on grade (SOG), Grid Lines 5 to 7 & B to D. (March 18, 2005)

View looking NE. (March 21, 2005)

SW corner of Bldg, Steel & roof bar joists. (March 21, 2005)

Central portion of bldg. looking N. (March 21, 2005)

Steel for East end of Bldg. on E. (March 21, 2005)

East end of Bldg. (March 21, 2005)

West end of Bldg. looking N. (March 21, 2005)

East end of Bldg. (March 24, 2005)

Central portion of bldg. looking N from MST OB roof. (March 24, 2005)

Central portion of bldg. looking N from MST OB roof. (March 24, 2005)

West end of bldg. - View looking N from MST OB roof. (March 24, 2005)

West end of bldg. - View looking N from MST OB roof. (March 24, 2005)

View looking NE. (March 24, 2005)

View looking S at Main Entry. (March 24, 2005)

View looking SSW. (March 24, 2005)

Prep. to pour last Slab on Grade (SOG) - Looking SE from 8" SOG, area of grid lines 3,4 and B,C. (March 24, 2005)

Prep. to pour last SOG - SW corner of Bldg. (March 24, 2005)

Prep. to pour last SOG - Grid lines 3,4 & B,C. (March 24, 2005)

View looking West. (March 24, 2005)

SW corner of bldg. - Grid Lines 2-5 & A-C

SW corner of bldg. - Grid Lines 2-5 & A-C

SW corner of bldg. - Grid Lines 2-5 & A-C

SW corner of bldg. - Grid Lines 2-5 & A-C

Bar joists are being installed on the ceiling area on the west side. See photo 1 for a view to the north from the 2nd floor window of the MSTOB. (March 23, 2005)

View looking to the northeast from the same location. (March 23, 2005)

View to the northwest from near the southeast corner of the fenced area. (March 23, 2005)

View to the southwest from Eniwetok Rd. (March 23, 2005)

First floor area yet to be poured, from row A to row C, and column 2 to column 5. (March 25, 2005)

This shows the view to the north and you can see good progress in placing the structural steel and the roof bar joists. Welding is in progress. (March 28, 2005)

Photo #2 shows the view from the 2nd floor window of the MSTOB, looking down at the new concrete which is 5 inches thick. (March 28, 2005)

This photo shows a view to the northeast. (March 28, 2005)

There will be a limited pour today @ 1 pm on the base of the west wall--you can see some forming in photo #4. The workers are also grouting the structural members in the little diamond shaped boxes at the mounted positions at the SOG. (March 28, 2005)

Looking generally northwest. (March 28, 2005)

Looking generally northwest. (March 28, 2005)

Looking generally northwest. (March 28, 2005)

View looking W. (3/31/05)

View looking NW. (3/31/05)

Steel Erection. (3/31/05)

View looking NW from SE corner of MER. (3/31/05)

Steel Erection. (3/31/05)

Pouring Diamonds @ Columns. (3/31/05)

View looking SW. (3/31/05)

View looking NNW. (3/31/05)

View looking SW. (3/31/05)

View looking SW. (3/31/05)

View looking SW, NW Corner of Bldg. (3/31/05)

View looking SE, Main Entry. (3/31/05)

View Looking NE. (3/31/05)

Central portion of Bldg. (3/31/05)

East end of bldg. and site. (3/31/05)

East end of site looking NE. (3/31/05)

View looking NE. (3/31/05)

Placing SOD gridlines 2 -4 & F to C.5. (4/15/05)

Placing SOD gridlines 2 -4 & F to C.5. (4/15/05)

West end of structure - backfilling W & S ret./stem walls. (4/15/05)

Structure looking NE -- roof decking in progress. (4/15/05)

Structure looking S. (4/15/05)

Structure looking WNW. (4/15/05)

View looking NW -- 7,D Intersection. (4/15/05)

Columns for rock faced wall. (4/15/05)

Structure looking SE. (4/15/05)

Studs delivered on 4/12/04 - Approx. 50%. (4/15/05)

Structure looking WNW. (4/15/05)

Structure looking NW. (4/15/05)

Second Floor - last SOD pour. (April 29, 2005)

Bldg. looking NE. (April 29, 2005)

Worker on scissor lift - installing studwall sm anchor. (April 29, 2005)

MER looking SW. (April 29, 2005)

First Floor - ductwork being installed - large elbows on floor. (April 29, 2005)

Second Floor - last concrete pour. (April 29, 2005)

Second Floor - last pour - looking SW. (April 29, 2005)

Mgt. Walk-Around by (L-R) C. Mangeng, ADTS; M. Strevell, PM-DO; J. Johnson, HPCC; P. Subba, HPCC; D. Chastain, PM-DO; on second floor looking SE [Thought HPCC STOP Program implemented very well]. (April 29, 2005)

Second Floor - last pour - east end. (April 29, 2005)

Second Floor looking NW towards main entry. (April 29, 2005)

Second Floor SW corner. (April 29, 2005)

Second Floor - Looking SW. (April 29, 2005)

Second Floor - in-slab electrical. (April 29, 2005)

Second Floor - in-slab electrical. (April 29, 2005)

View looking mostly S -- most building w/two floors. (April 29, 2005)

View from 2nd flr. MST-OB looking NE -- Note east of second floor just poured. (April 29, 2005)

SW corner of bldg. @ MER -- Excav. for domestic water main to bldg. - Fire Water Line visible inside MER. (April 29, 2005)

View looking N from MST-OB first floor -- West end of bldg. (April 29, 2005)

View looking NE from MST-OB first flr. -- Note ductwork in MER. (April 29, 2005)

Fire Protection water line in place and tested (on left) -- main bldg. domestic water supply installed parallel to FW line (on right). (April 29, 2005)

View looking NE -- stud progess -- excav. for domestic water main to bldg. (April 29, 2005)

View looking SE from Eniwetok Dr. (April 29, 2005)

View looking S -- stone veneer wall in foreground. (April 29, 2005)

View looking mostly S -- most building w/two floors. (April 29, 2005)

View looking SW -- Steel stud installation in progress. (April 29, 2005)

View looking W @ S end of building. (April 29, 2005)

Sidewalk just West of MST-OB ready for pour. (May 20, 2005)

View looking NNE - Sidewalk being readied for pour. (May 20, 2005)

View looking E. (May 20, 2005)

View looking mostly S. (May 20, 2005)

View looking SE. (May 20, 2005)

View looking SSW. (May 20, 2005)

View looking SW. (May 20, 2005)

View looking W. (May 20, 2005)

L-R: T. Taylor, MST-CINT; Jesse Johnson, HPCC; Don Rey, ADSR; Brigg Lichfield, HPCC; -- First floor looking W @ Lab area. (May 20, 2005)

Second Floor looking E. (May 20, 2005)

Second Floor interior looking E. (May 20, 2005)

Second Floor West Wall looking NNW. (May 20, 2005)

Second Floor interior looking NE. (May 20, 2005)

Permanent Electr. Power ductbank from MST-OB roof. (May 20, 2005)

Permanent Electr. Power ductbank (poured today) from MST-OB roof. (May 20, 2005)

Sheathing above Comp. Rm. looking N. (May 20, 2005)

View looking NE from MST-OB roof. (May 20, 2005)

Permanent Electr. Power Ductbank poured today - temp. power at bottom of photo. (May 20, 2005)

Domestic & Fire Protection Water ready to tie-in to LANL system - mat'ls by contr. - tie-in by KSL. (May 20, 2005)

Main entry looking East. (June 14, 2005)

Reviewers near main entry on first floor between stairs and elevator. (June 1, 2005)

Reviewers with elevator in background looking NW. (June 1, 2005)

Reviewers with elevator in background looking NW. (June 1, 2005)

Reviewers just outside (West of) the Gateway main entry. (June 1, 2005)

Reviewers just outside (West of) the Gateway main entry. (June 1, 2005)

Forming for retaining wall between Gateway and MST-OB (See IMG_0623.JPG). (June 14, 2005)

West side of building looking ENE. (June 14, 2005)

Main entry looking East. (June 14, 2005)

Bldg. looking West. (June 14, 2005)

Bldg. looking SE from Eniwetok (main entry). (June 14, 2005)

Bldg. looking SE from Eniwetok. (June 14, 2005)

Communications ductbank looking SE from building. (June 14, 2005)

Window installation at main entry. (June 14, 2005)

Ductwork, piping,etc., near MER. (June 14, 2005)

Corridor 1200D looking West. (June 14, 2005)

Bldg. interior at NW corner looking West. (June 14, 2005)

N.E. corner of bldg. looking. (June 14, 2005)

Preparation for seaming of standing seam roof. (June 14, 2005)

Forming for retaining wall between the Gateway and the MST-OB. (June 14, 2005)

Slab for permanent electrical transformer on S. side of buiding. (June 14, 2005)

Forming standing seam roofing material. (June 14, 2005)

Roofing installation over MER. (June 14, 2005)

Forming for retaining wall between Gateway and MST-OB/Slab for Electrical Transformer. (June 14, 2005)

Communications Ductbank Route to manhole - transite line at lower right. (June 15, 2005)

SE end of building - communications line backfill and clearing of gas cylinder storage area. (June 15, 2005)

Slab for permanent power on right - temp. power @ lower right. (June 15, 2005)

Forming for wall between Gateway and MST-OB -- Roofing material ready for installation. (June 15, 2005)

Standing Seam roofing material & Exhaust Stack. (June 15, 2005)

S.E. end of site -- Concr. Pumper for wall between CINT & MST-OB. (June 21, 2005)

Tie-in point for building Fire Hydrant on east end of building -- taken from east MST-OB 2nd flr. window. (June 21, 2005)

Pouring wall between CINT & MST-OB. (June 21, 2005)

Southern area of building -- Concr. Pumper for wall between CINT & MST-OB. (June 21, 2005)

Wall between CINT & MST-OB -- Permanent building transformer in place. (June 21, 2005)

Permanent CINT transformer in place. (June 21, 2005)

Pouring wall between CINT & MST-OB. (June 21, 2005)

Building looking NE -- Roof panels in foreground. Wall panels & stacked stone in progress. (June 30, 2005)

Building looking ENE -- stacked stone in progress. (June 30, 2005)

Rear of building looking NE -- Scaffolding being placed. (June 30, 2005)

Building looking SE. (June 30, 2005)

Building & entry looking SE. (June 30, 2005)

North side of building looking SSE. (June 30, 2005)

Standpipe for Sanitary Sewer test. (June 30, 2005)

Trench for Communications Ductbank -- Transite pipe removed. (June 30, 2005)

Building looking NW -- South area. (July 1, 2005)

Building looking NW -- East area. (July 1, 2005)

Corridor 1200D -- Looking West. (July 1, 2005)

Equip. Rm. -- 1st floor -- Looking W. (July 1, 2005)

Equip. Rm. -- Looking SW. (July 1, 2005)

Entry -- First Floor -- Looking N. (July 1, 2005)

Entry -- Stairway -- taken from 2nd Flr. (July 1, 2005)

Corridor 2000A -- Looking S. Computational Graphics to the left (Rm 2301). (July 1, 2005)

Exhaust Stack (42") in Mech. Equip. Rm. -- 2nd Flr. (July 1, 2005)

Mech. Equip. Rm. -- 2nd Flr. (July 1, 2005)

Ductwork in 2nd Flr. Mech. Equip. Rm. (July 1, 2005)

1st Flr. -- Spectroscopy/Novel Optical Scanning Probe, Rm. 1201 -- looking East. (July 1, 2005)

Rock wall near entry at street (Eniwetok) taken from inside building looking down and to the North. (July 1, 2005)

Building looking West -- looking at East Wall. (July 1, 2005)

SE end of building -- looking N -- prep. for plastering. (July 8, 2005)

SW end of building -- looking N prep. for plastering. (July 8, 2005)

Prep. for lifting SS roofing panels. (July 8, 2005)

Prep. for lifting SS roffing panels. (July 8, 2005)

Lifting SS roofing panels. (July 8, 2005)

Lifting SS roofing panels -- looking NNE. (July 8, 2005)

Side Metal Panel/Stacked Stone in progress -- Prep for plastering SW corner. (July 8, 2005)

Lifting SS roof panels -- looking NNE. (July 8, 2005)

Lifting Standing Seam (SS) roofing panels. (July 8, 2005)

Building Entry looking SE - lifting SS roofing panels. (July 8, 2005)

View of Building looking SE. (July 8, 2005)

View of Building looking SE. (July 8, 2005)

Excavation for East Fire Hydrant tie-in - upper left where conduit was damaged - now covered by mud - behind PIV conduit shown. (July 18, 2005)

Bldg. looking NW - plaster scratch coat in progress. (July 18, 2005)

Bldg. looking W - plaster scratch coat in prgress. (July 18, 2005)

First Floor Corridor (1200B) looking W - Mech in progress - temp. task lighting. (July 18, 2005)

Plaster scratch coat outside Recieving Area/Loading Dock (Rm. 1216) & outside men's bathroom - looking SSW. (July 18, 2005)

Outdoor mtg. area - First Floor - Rm. 1130 - looking NE. (July 18, 2005)

Manager's Office (Rm. 2117A) - Second Flr. - NW corner wall sheet rocked both sides. (July 18, 2005)

Corridor 1200A looking S --Door on left is to Rm. 1217 - X-Ray Diffraction or "Physical Synthesis". (July 18, 2005)

View from second floor looking NNE - stacked stone wall at entry starting. (July 18, 2005)

Synthesis (Rm. 2204) looking E. (July 18, 2005)

Second Floor looking E from just North of evevator. (July 18, 2005)

Biochem./Molecular Biology - Rm. 2201. (July 18, 2005)

MER looking SE. (July 18, 2005)

Corridor 1200D looking E - Rm. 1201, Spectroscopy/Novel Optical Scanning Probe to the near right. (July 18, 2005)

Building looking WSW, Tyvec installation nearing completion. (July 18, 2005)

Bldg. looking SW - metal siding, roofing, stacked stone in progress . (July 18, 2005)

Bldg. looking SE - Metal siding, roofing, stacked stone in progress. (July 18, 2005)

Area of East Fire Hydrant tie-in. (July 18, 2005)

SS roof installation over first floor. (July 26, 2005)

Bldg. looking SW - window installation - prep. for curb & gutter. (July 26, 2005)

Bldg. looking E at entry - discussing taxi drop-off modification. (July 26, 2005)

Fire hydrant routing on east end of site. (July 26, 2005)

Last of communications ductbank - Communications M.H. behind porta-potti. (July 26, 2005)

Fire hydrant at east end of site in progress. (July 26, 2005)

East end of bldg. looking NNE from MST-OB roof. (July 26, 2005)

Back center of bldg. looking North from MST-OB roof. Plastering in progress. (July 26, 2005)

Back of bldg. looking NW from MST-OB roof. (July 26, 2005)

West end of bldg. from MST-OB roof. Sidewalk in place. Plastering in progress. (July 26, 2005)

West end of second floor roofing installation. (July 26, 2005)

Bldg. looking NE from MST-OB roof. (July 26, 2005)

SW back wall -- Tyvec install. over MER -- scaffolding for stucco. (July 29, 2005)

Prep. for stuccoing SW back wall. (July 29, 2005)

Stucco in progress on S. wall. (July 29, 2005)

Stucco in progress on S. wall -- scaffolding being removed with progress. (July 29, 2005)

Forming for stairs at entry. (July 29, 2005)

Preparation for concrete at entry -- stacked stone wall in progress. (July 29, 2005)

Bldg. looking SE. (July 29, 2005)

Bldg. looking SE -- Roofing in progress. (July 29, 2005)

East end of bldg. looking SE -- Roofing in progress -- Window inst. in progress. (July 29, 2005)

Backfilling fire protection line at east end of site for fire hydrant -- looking SW. (July 29, 2005)

Installation of fire hydrant -- east end of site. (July 29, 2005)

Damaged electrical conduit from excavation for fire protection line - hydrant inst. (July 29, 2005)

Fire hydrant water line ready for tie-in -- exist main at bottom of photo. (July 29, 2005)

Back of Bldg. looking NW -- stuccoing in progress. (July 29, 2005)

Break Room/Coffe Bar/Kithenette looking W from Outdoor Meeting Area -- Bar framework in progress. (July 29, 2005)

View looking W from Interactive Commons area (1000B) towards Corridor (1100). (July 29, 2005)

Forming for stairs at entry. (July 29, 2005)

Temp. Staff Off. (1302) looking S. (July 29, 2005)

MER (1402) looking W. (July 29, 2005)

Second Floor looking East -- Elevator on the right. (July 29, 2005)

NW corner of Biochemistry/Molecular Biology Lab (Rm. 2201) -- looking SE. (July 29, 2005)

Forming for retaining wall and stairs at entry. (July 29, 2005)

Ductwork up from first floor to second floor at chase - looking N. (July 29, 2005)

Prep. for drywall at stairway (2300S2) from second floor -- looking E. (July 29, 2005)

Roof over first floor taken from Manager's Office (2117A) -- Looking SE. (July 29, 2005)

Roof over first floor taken from Manager's Office. (July 29, 2005)

View looking W from Manager's Office (2117A) - N windows on right. (July 29, 2005)

Bldg. looking SW. (July 29, 2005)

Bldg. looking WSW. (July 29, 2005)

Stuccoing wall between CINT and MST-OB -- looking ENE. (July 29, 2005)

East fire hydrant tie-in looking N -- partially covered -- thrust blocks -- gate valve on new line. (August 8, 2005)

Damaged conduit in trench for fire hydrant water piping. (August 8, 2005)

Back of bldg. looking NW. (August 8, 2005)

SE end of bldg. looking NNW. (August 8, 2005)

Back of bldg. looking W. (August 8, 2005)

East end of bldg. looking S. -- First floor roof in progress -- prep. for drainage on North -- Looking South. (August 8, 2005)

NE end of bldg. -- first floor roof in progress -- Prep. for north area drainage. (August 8, 2005)

NW end of bldg. -- prep. for N. drainage. (August 8, 2005)

Bldg. looking SE. (August 8, 2005)

Entry looking E. (August 8, 2005)

Retaining wall at entry -- Area drain ready for install. (August 8, 2005)

West end of bldg. looking NE. (August 8, 2005)

Prep. for stairs and plaza at entry -- looking SE. (August 17, 2005)

Bldg. looking SE -- stacked stone & curb & gutter installation prep. on Eniwetok Dr. (August 17, 2005)

East end of bldg. looking NNW. (August 17, 2005)

South of bldg. looking W. (August 17, 2005)

Corridor 1100 looking W -- W -- North corr. (August 17, 2005)

Corridor 1200D - looking W - Center Corr. (August 17, 2005)

Continuing work on stacked stone wall at entry -- looking N from stairwasy inside kkl. (August 17, 2005)

Prep for stairs and plaza at entry -- looking NW from second floor of Gateway. (August 17, 2005)

Synthesis Lab -- Rm. 2204. (August 17, 2005)

Manager's Office looking NE. (August 17, 2005)

Eniwetok Dr. & bldg. looking W -- curb & gutter prep. (August 17, 2005)

1st to 2nd Flr steel panel installation - N end of bldg. looking SW. (August 17, 2005)

Bldg. looking SE. (August 17, 2005)

Counter in kitchenette/breakroom/coffee bar Rm. 1123. (August 31, 2005)

Kitchenette, Rm. 1123 looking West. (August 31, 2005)

Corridor 1100 looking West. (August 31, 2005)

Interactive/Commons 1100B looking W towards entrance. (August 31, 2005)

MER looking W -- Fabricated piping on floor. (August 31, 2005)

Shower Rm. 1316 looking South. (August 31, 2005)

Unisex Bathroom 1310 looking West. (August 31, 2005)

Corridor 1300 looking West from grid line 5. (August 31, 2005)

Ret. walls/stairs at entry looking South. (August 31, 2005)

Curb & Gutter & sidewalk looking E on Eniwetok from entry. (August 31, 2005)

Curb & Gutter prep. & other work at entry looking SE. (August 31, 2005)

Stud wall at entry on second floor near elevator looking North. (August 31, 2005)

Door & wall at kitchenette at entry on second floor looking East. (August 31, 2005)

Biochemistry/Molecular Biology Rm. 2201 looking SE. (August 31, 2005)

Outside Computer Graphics Rm. 2301 (to the left) and looking E down corridor 2300. (August 31, 2005)

Computer Lab Server Rm. 2302 (looking SE) being used as fabrication area. (August 31, 2005)

Air Handling Unit in MER Rm. 2402. (August 31, 2005)

Air Handling Unit in MER Rm. 2402 looking West . (August 31, 2005)

Corridor 2200 looking W from corridor 2200A. (August 31, 2005)

Trench for steam & condensate line at entry to equipment room. (August 31, 2005)

Excavation for steam & condensate line - finishing at expansion loop. (August 31, 2005)

Excavation for steam & condensate line - finishing at expansion loop - steam manhole at right. (August 31, 2005)

Bldg. & roof at W. end - finishing standing seam roofing details. (August 31, 2005)

East end of bldg -- view of roof. (August 31, 2005)

Steam and condensate line at entry to equipment room. (August 31, 2005)

Steam and condensate trench - beginning sandbed - looking towards the steam manhole. (August 31, 2005)

Steam and condensate trench @ exp. loop -- beginning sandbed. (August 31, 2005)

Steam and condensate trench towards steam manhole. (August 31, 2005)

Steam and condensate trench from manhole towards MER. (August 31, 2005)

Computational Graphics Rm. 2301. (August 30, 2005)

Computational Graphics Rm. 2301 looking N. (August 30, 2005)

Excavation for steam and condensate lines - steam and condensate lines in foreground. (August 30, 2005)

Secondary conduit hit during fire water line excavation needing to be repaired within orange fence. (August 30, 2005)

Excavation for steam and condensate lines - Low point vault to be installed where worker in trench is. (August 30, 2005)

Excavation for steam and condensate lines. (August 30, 2005)

East end of bldg. looking N. (August 30, 2005)

Curb & Gutter prep. @ main entry - finishing roofing details. (August 30, 2005)

Curb & Gutter prep. @ main entry. (August 30, 2005)

AHU in MER. (August 30, 2005)

SWPPP needs to be addressed -- looking E just E of construction site entry. (August 31, 2005)

Bldg. looking SW - Note curb and gutter along Eniwetok. (August 31, 2005)

Bldg looking SE. (August 31, 2005)

Bldg entry looking SE. (August 31, 2005)

East end of site looking N - prep for asphalt. (September 29, 2005)

SE end of buildign looking N. (September 29, 2005)

Bldg looking N - concrete work at entry. (September 29, 2005)

Chiller set on pad, site preop for asphalt. (September 29, 2005)

HVAC Fans on West sidewalk. (September 30, 2005)

West side of Bldg. looking NE. (September 30, 2005)

Main Entry looking SE. (September 30, 2005)

Main Entry looking SE. (September 30, 2005)

Bldg. looking NW - drainage trench - curb & gutter. (September 30, 2005)

Storm drains at Eniwetok. (September 30, 2005)

Site looking SW - curb & gutter inst. (September 30, 2005)

Break Rm./Coffee Bar/Kitchenette Rm. 1123 looking NNW. (September 30, 2005)

Entry to Informal Meeting/Teleconference Rm. 1126. (September 30, 2005)

Spectroscopy/Novel Scanning Probe Rm. 1201, looking NE, casework (purple). (September 30, 2005)

Corridor 1200 looking E. (September 30, 2005)

Corridor 1200 - Doors to Loading Dock. (September 30, 2005)

Manager's Office Rm. 2117A looking E. (September 30, 2005)

Biochem./Molecular Biology Rm. 2201 looking SE. (September 30, 2005)

Concrete Work at Entry. (September 30, 2005)

Steam Vault outside MER. (September 30, 2005)

Gateway to Los Alamos facility site visit - Attendees: Toni Taylor, Julie Phillips, SNL; R. Stolen, SNL; J. Roberts, M. Nastasi, P. Follansbee, Michael Lilly, SNL; Tom Picraux, Richard Averitt, John Sullivan, SNL. (October 5, 2005)

Stubouts installed for Steam & Condensate tie-ins inside existing steam manhole. (October 5, 2005)

Prep. for asphalt, SE side, looking NW. (October 5, 2005)

Prep. for asphalt between CINT and MST-OB, looking W. (October 5, 2005)

Curb & Gutter - SE side - looking N. (October 5, 2005)

E side of site looking SW - prep. for asphalt. (October 5, 2005)

Curb & Gutter looking W @ Eniwetok. (October 5, 2005)












Casework in Nano Fluidics/LB Thin Films (Rm. 1225). (October 31, 2005)

Casework & biosafety cabinet in Nano Fluidics/LB Thin Films (Rm. 1225). (October 31, 2005)

Casework in Physical Sythesis Rm. (Rm. 1217). (October 31, 2005)

Corridor 1200D from 1200A looking W. (October 31, 2005)

Casework in Spectroscopy/Novel Optical Scanning Probe Rm. (Rm. 1201) - looking NW. (October 31, 2005)

Interactive Commons area (1100B) looking SE. (October 31, 2005)

Break Rm./Coffee Bar (1123) looking W. (October 31, 2005)

Kitchenette/Library (Rm. 2001). (October 31, 2005)

Conf. Rm. (Rm. 2101) looking SE. (October 31, 2005)

Windows into Biochemistry/Molecular Biology (Rm. 2201). (October 31, 2005)

Corridor (2200) looking NW from Corr. 2200A - just W of rm. 2123. (October 31, 2005)

Computer Lab & Server Rm. (Rm. 2302). (October 31, 2005)

NW Plaza looking NW from second floor window - landscaping in progress. (October 31, 2005)

Mech. Equip. Rm. (MER), First Floor looking SW, outside (at grade level) grate is opening for steam vault. (October 31, 2005)

Entry looking SE. (October 31, 2005)

Informal Meeting/Teleconf. Rm. 1126.

Furniture in typical office. November 15, 2005

Cabinetry in Copy/Print Rm. 1120.

Tilework at main entry. November 15, 2005

Stairway at SE end of bldg. November 15, 2005

Furniture in Data Analysis Area 2300C looking WSW. November 15, 2005

Computer Rm. 2302. November 15, 2005

Conf. Rm. 2101 - Divider & screen. November 15, 2005

Furniture in typical office. November 15, 2005









Basecourse prep. for asphalt. (October 17, 2005)

Hood & Casework in lab. (October 17, 2005)

Prep for asphalt, curb & gutter. looking SW from near E. fire hydrant. (October 17, 2005)

Bldg. looking W. (October 17, 2005)

E. site looking SW from constr. site entry. (October 17, 2005)

Casework in lab. (October 17, 2005)

Casework in lab. (October 17, 2005)

Kitchenette/Library looking SE (Rm. 2001). (October 17, 2005)

Raised floor in Computer Rm. (Rm. 2302). (October 17, 2005)

Bio/Environmental Rm. (Rm. 2207B) looking N. (October 17, 2005)

Meeting/Congregation Area (2100B) looking W. (October 17, 2005)

Entry looking N. (October 17, 2005)

Bldg. looking SE. (October 17, 2005)

Bldg. looking SE. (October 17, 2005)

Bldg. looking E. (October 17, 2005)

Bldg. looking E @ Entry. (October 17, 2005)

Entry/Plaza area looking SSE. (October 17, 2005)

East end of site w/asphalt primer in place. (October 31, 2005)

Roofing w/snow stops & lightning rods - upper SE corner of roof. (October 31, 2005)

East end of bldg. looking N. (October 31, 2005)

West end of bldg. looking N. (October 31, 2005)

Plaza area at entry looking NNW - Roof of MER at right. (October 31, 2005)

West side of entry area looking NE. (October 31, 2005)

Entry looking NE. (October 31, 2005)

Entry looking E. (October 31, 2005)

Bldg. looking SE. (October 31, 2005)

Bldg. looking SE. (October 31, 2005)

Bldg. looking NW. (October 31, 2005)

Casework in Synthesis Rm. 2204.

Fume hood in Synthesis Rm. 2204. November 15, 2005

E. end of bldg. - looking W. November 15, 2005

Bldg. looking NNW. November 15, 2005

Bldg. looking SE - landscaping along Eniwetok. November 15, 2005

Entry looking ESE. November 15, 2005

Small curb pour @ entry plaza.

Bldg. looking SE

Bldg. looking SW. November 15, 2005

West end of bldg. near entry - landscape trees. November 15, 2005

Bldg. looking N. from MST-OB - landscaping trees to right. November 15, 2005

Landscaping in W front of MST-OB looking towards Gateway. (November 30, 2005)

Landscaping in W front of Gateway Bldg. - Gateway looking NE. (November 30, 2005)

Main Entry looking E. (November 30, 2005)

Main Entry looking E. (November 30, 2005)

Bldg. looking SE. (November 30, 2005)

Bldg. looking ESE. (November 30, 2005)

E side of Bldg. looking W. (November 30, 2005)

Nano Fluidics/LB Thin Films, Rm. 1225, 6' Biosafety Cabinet. (November 30, 2005)

Self Assembly, Rm. 1221, E. wall, 6' Fume Hood. (November 30, 2005)

Spectroscopy/Novel Optical Scan. Probe, Rm. 1201. (November 30, 2005)

Main Entry, first floor, looking N. (November 30, 2005)

Admin. Support Off, 1102, looking SW. (November 30, 2005)

Interactive Commons Area, 1100B, looking E. (November 30, 2005)

Break Rm./Coffee Bar/Kitchenette, 1123. (November 30, 2005)

Entry @ 2nd flr. looking S, windows to left are to Biochemistry/Molecular Biology, Rm. 2201. (November 30, 2005)

Please be aware that this is a DOE facility and additional access restrictions may apply.

Conf. Rm. 2101, lookin E. (November 30, 2005)

Mtg./Congregation Area 2100B. (November 30, 2005)

Typ. Off., second flr., N. (November 30, 2005)

Manager's Office, Rm. 2117A. (November 30, 2005)

Environmental Room (4 deg. C.), Rm. 2207B. (November 30, 2005)

Biosafety Cabinet, Rm. 2207E, Bacteria Cell, looking NE. (November 30, 2005)

Synthesis, Rm. 2204. (November 30, 2005)

Synthesis, Rm. 2204. (November 30, 2005)

Data Analysis Area, 2300C, looking E, towards corridor 2300. (November 30, 2005)

Triple exhaust fan connection in 2nd flr. MER to 42" bldg. exhaust stack. (November 30, 2005)

Finish grade gravel top between Gateway Chiller and Gateway Bldg. - Gateway electr. xfmr. behind chiller. (November 30, 2005)

Finish grade gravel top between MST-OB and Gateway Chiller - MST-OB electr. xfmr. on left, Gatew